Site C work camp construction nears completion in April 2016. Called Two Rivers Lodge, the camp cost $470 million to build and operate and is a self-contained community with an 800-seat dining room, hair salon, gym, movie theatre and private room accommodations. (B.C. Hydro)

Environmental groups slam NDP decision to continue with Site C

Construction industry, meanwhile, is cautiously optimistic about how the project will look

Environmental groups denounced Premier John Horgan as he announced Monday the province would continue to build the Site C dam.

The Wilderness Committee told Black Press they were “massively disappointed” with what they called the NDP’s “flip-flopping” on the now-$10.7-billion northern B.C. megaproject.

“We can only come to the conclusion that Horgan was lobbied extensively by some of the construction unions,” said national campaign director Joe Foy.

READ: Site C dam goes ahead, cost estimate now up to $10.7 billion

According to the organization, the Site C dam could flood 83 kilometres of the Peace River from near Fort St. John upstream to Hudson’s Hope, contaminating fish stocks, and remove farmland from the Agricultural Land Reserve.

Foy took issue with the province’s claim that it would have cost $4 billion to halt the project, as well as Horgan’s stance that that money could not be paid back over time.

“We believe that is grossly overestimated,” he said. “All that dam can do, unlike the hole in the ground which just sits there, is lose us hundreds of millions of dollars every year it operates.”

He said the NDP’s decision could change B.C.’s political landscape as NDP voters who may feel betrayed move away from the party. Horgan had campaigned earlier this year on a promise to review, not kill, the dam, but he had criticized the BC Liberals’ approach to the project in the past.

More lawsuits expected

Court challenges, Foy said, are likely coming both from environmental and First Nations groups.

“I think rolling over First Nations in this way is unacceptable,” he said. “I think we will begin to see the effects of protests.”

Amnesty International called Horgan’s decision “a blatant betrayal of his government’s commitments to uphold the rights of Indigenous peoples.”

The group called foul on the province’s claim that it was too late to stop the project and said the West Moberly and Prophet River First Nations will continue their legal efforts.

‘We are relieved’

Meanwhile, the Independent Contractors and Businesses Association celebrated the thousands of jobs they believe will be kept and created by continuing work on Site C.

Spokesperson Jordan Bateman said all the extra time the NDP government took to have the dam reviewed was unnecessary, only to have Horgan ultimately go forward.

READ: BC Utilities Commission completes Site C report

Bateman said he also doesn’t buy the province’s new $10.7-billion estimated price tag. When it was approved by the then-Liberal government in 2014, the project was estimated at $8.8 billion.

“You have one analysis done in six weeks that says it could run over budget,” he said. “Frankly, the overruns that the NDP are planning for here are going to be caused by the NDP.”


@katslepian

katya.slepian@bpdigital.ca

Like us on Facebook and follow us on Twitter.

Just Posted

More burning prohibitions rescinded in southeast B.C.

Category 2 and 3 fires will be permitted in Southeast Fire Centre as of 1p.m. on Wednesday.

B.C. parents leery of HPV cervical cancer vaccine

Provincial registration uptake among lowest in Canada

Municipal spending outpaces population growth 4-fold in B.C.: report

Canadian Federation of Independent Business has released its annual operational spending report

Winlaw preemie survives smoky birth

GoFundMe Campaign started for West Kootenay family with preemie baby.

Youth on the Loose: Centre takes trip to Whatshan Lake

The trip was organized by the Nakusp and Area Youth Network

Conservation officer frees B.C. deer from flotation gear mishap

BC Conservation Officer Service is reminding residents to keep backyards clear of entanglements

Ottawa to name new ambassador for women, peace and security, Freeland says

Chrystia Freeland also confirmed Canada would spend about $25 million to fund number of initiatives

‘A little bright spot:’ Ottawa residents rescue dog trapped beneath rubble

Freelance journalist says rescue of a dog trapped under rubble was happy ending amid chaos in Ottawa

B.C. deaf community wants different sign languages on federal accessibility act

Advocates also want Indigenous Sign Language to be recognized on the Indigenous Language Act

VIDEO: B.C.-born firefighter remembered by MP in emotional speech

Family asks first responders to look after one another in wake of suicide, growing concerns of PTSD

Airline has ‘close call’ with drone while en route to B.C. airport

Jazz Aviation reported the drone sighting near Vancouver to the RCMP and Transport Canada

Tragic accident claims life of B.C. toddler

Fundraising effort has been created to help mom and family

B.C. nanny charged with sex abuse of 3 children

Saanich Police seek potential victims of Johnathon Lee Robichaud from Central Saanich

‘I’m no quitter’ on climate change issues, McKenna says at G7 ministers meeting

David Suzuki says if McKenna believes what she’s saying, she too should quit

Most Read