Trans Mountain pipeline expansion work near Jasper Alberta

Long list of conditions for Trans Mountain approval

Kinder Morgan says 145 conditions on wildlife, ocean impact, earthquake and other hazards is "rigorous but achievable"

The National Energy Board has released a draft list of 145 conditions for approval of Kinder Morgan Canada’s oil pipeline expansion project, including environmental protection plans for land and marine operations.

Conditions include the possibility of dredging for the expansion of the Westridge Marine Terminal in Burnaby, where the original Trans Mountain pipeline has delivered crude oil and refined products since 1953.

Kinder Morgan is proposing to twin the line to ramp up shipments of diluted bitumen from northern Alberta that began intermittently in the late 1980s. The $5.4 billion expansion project would nearly triple the line’s capacity to 890,000 barrels per day, resulting in a seven-fold increase in oil tankers entering and leaving Vancouver harbour.

Kinder Morgan Canada president Ian Anderson said Thursday the company will be seeking clarification on the timing of some of the conditions, and will file its comments to the NEB review panel Aug. 20. Most major conditions, including plans for watercourse crossings along the route, are to be filed at least 90 days before construction begins.

“Our initial review of the draft conditions is that they are rigorous but achievable,” Anderson said.

NEB hearings are to resume Aug. 24, where the B.C. government is expected to formalize its position, based on Premier Christy Clark’s five conditions for new heavy oil pipelines. They include a “world-class” spill response capability on land and sea, approval and benefit sharing by affected First Nations, and a still-undefined “fair share” of benefits for the province.

Those conditions were included in B.C.’s position opposing the Enbridge Northern Gateway project, which the federal government approved with its own list of more than 200 conditions. The province does not have authority to veto either pipeline project, as each would run from Alberta to B.C.

Draft conditions for Trans Mountain include identification of all sites on the proposed second line affected by earthquake, including the “Holocene for Sumas Fault, Vedder Mountain Fault, Fraser River-Straight Creek Fault and Rocky Mountain Trench, as well as other possible hidden faults.”

Conditions also include submitting records of landowner consultation on the route, and a plan for aboriginal participation in monitoring construction.

 

Just Posted

Last of southern Selkirk caribou relocated to Revelstoke area

One cow from the South Selkirk herd and two from the Purcells were moved this week

How to stay safe in the Nakusp backcountry: BCSARA

The B.C. Search and Rescue Association recommends planning, training and taking the essentials

Skier caught in backcountry avalanche near Rossland

‘The man was lucky he had the ‘A-Team’ of ski patrol people able to respond as quickly as they did,’ says Rossland rescue spokesperson

Kootenays unemployment rate best in B.C.

In one year, the region has gone from highest unemployment rate to lowest, at 3.1 per cent

Nakusp search and rescue group seeks volunteers

Senior Nakusp SAR member Ross Shkuratoff says the group is on the lookout for new members

VIDEO: U.S. Congress to probe whether Trump told lawyer Cohen to lie

At issue is a BuzzFeed News report that about negotiations over a Moscow real estate project

Charges upgraded against mother of murdered B.C. girl

Kerryann Lewis now faces first- rather than second-degree murder in the death of Aaliyah Rosa.

Explosion sends B.C. firefighter to hospital

Kelowna fire crews responded to a blaze at Pope’sGallery of BC Art & Photography on Friday

Rare ‘super blood wolf moon’ takes to the skies this Sunday

Celestial event happens only three times this century

Arrest made after historic B.C. church hit by arson

The fire at the 150-year-old Murray United Church in Merritt was considered a possible hate crime

B.C. dangerous offender in court for violating no-contact order, sends letter to victim

Wayne Belleville was shocked to see a letter addressed to him from his shooter, Ronald Teneycke

Crowsnest Pass RCMP seek help locating missing man

58-year-old Stuart David Duff was last seen on Jan. 6, 2019.

Man blames his loud car radio, sirens for crash with B.C. ambulance

Tribunal rejects bid to recoup ICBC costs after crash deemed 100-per-cent his fault

RECALL: Salmon Village maple salmon nuggets

Customers warned not to eat product due to possible Listeria contamination

Most Read